Chris Stevens is an independent decorator Merchants with a ceramic tiling and bathroom supply arm.

Adept Building Services were approached by the directors to seek a price to demolish an existing building on the site which was previously a car showroom / workshops and to build a purpose built warehouse and showroom facility

This facility was to accommodate the bathroom and tiling division for both displays/ showroom and for holding extensive stock.

A price was agreed as a lump sum and works commenced.

The total build length was 10 months including demolition of the old warehouse, groundwork’s with piled foundations and polished concrete floor, steel superstructure with part bricked elevations and cladding to upper storey.  There was also a structural mid floor formed from steel supports with pre cast concrete planks and structural screed topping. Structural concrete staircases were installed as was a goods lift.

After the construction phase Adept carried out internal fitting out including suspended ceilings, dry lining and carpentry.

The last phases of works were the external package including drainage, roadways, perimeter fencing and external retaining walls.

The external works were carried out in 10 weeks and the business is now operating successfully.